15/05/25
Planned Maintenance Activities – Sunday, 18 May 2025
Dear All,
Please be informed of the following scheduled maintenance activities planned for Sunday, May 18th, from 08:30 AM to 03:00 PM as part of our Week 20 operations:
- Fiber Splicing – STS-08 - Impact: Power will be de-energized for STS-08, as well as STS-04/05.
- System Patching – NRA (Cybersecurity & EOL Update) - Impact: Interruption of N4 system; a temporary system stoppage is recommended during the patching process to ensure integrity and safety.
- Activate a new yard file for production; this can be combined with either N4 system stoppage.
- Apache upgrade for LB TOS system.
We appreciate your understanding and support as we carry out these essential upgrades and maintenance efforts to enhance system reliability and security.
Please don't hesitate to reach out if you have any concerns or require further details.
Best regards,
IT department